The rollout of TLS1.2-only on Windows servers is largely complete, with a handful still pending for various reasons.
Approximately 25 servers in the Banner environment will be migrated to HCI between now and July 18. The Admin Computing Advisory Committee has been informed of the schedule.
Network upgrades in Buchanan Towers is underway.
Degree Works will go down for an upgrade this Friday night.
Delayed until 7/13: EIS plans to enable Quarantined Email notifications to end-users on a weekly cadence. Once per week, if a user has messages in their Quarantine, they will receive an automated email from the ATUS Help Desk informing them of how to check Quarantine, delete malicious emails, and release false positives.
The legacy static website service known as Campus Web will be decommissioned on or after 12/31/23. ATUS, WebTech, and distributed IT will work with site owners to migrate any sites on Campus Web that need to stay online.
See the PMO CJIS and Risked Based MFA Are Rolling Out
CISCO Identity Services Engine Updates
CISCO DNAC UIpdates
Banner Upgrade Scheduled for 10/28-29
Kaiser-Bosari Hall Network Installation Continues
Microsoft SQL Server Upgrade has been Postponed
See the Project Management Office web page at https://eas.wwu.edu for updates on current enterprise IT projects.